Why Grafton’s Pleasant Street Bridge reopening was delayed in 2009

Why Grafton’s Pleasant Street Bridge reopening was delayed in 2009

On June 30, 2009, Massachusetts highway officials postponed the expected reopening of Grafton’s Pleasant Street Bridge. Concrete in the structure differed from project specifications, prompting an engineering review, according to the original Grafton Times report.

The last-minute delay came near the end of a much longer effort to replace the crossing over the Blackstone River. An earlier construction contract had ended, a new team had taken over, and town officials had spent the spring addressing access to nearby property and pressing for sidewalks.

A century-old crossing and an interrupted project

The bridge being replaced was a masonry arch built in 1909. Massachusetts’ bridge inventory keeps separate entries for that removed structure and its concrete-arch replacement, built a century later.

The first replacement project had received its notice to proceed on May 3, 2005. Its original description called for a new bridge beside the old one, allowing traffic to continue using the existing crossing during construction. Work behind the retaining walls was intended to limit environmental effects. A July 27, 2006, state update described the bridge as closed during utility-support work and gas-main relocation preparations.

The same record labels the first construction contract terminated. It does not explain the termination. This dated history places the disruption well before the June 2009 announcement, although it does not establish the first day of closure or whether the bridge stayed closed throughout every phase.

A new contract and plans to reuse the old stone

The next phase appeared in the state’s project records in autumn 2008. Massachusetts advertised the work on October 18 and issued a notice to proceed on February 4, 2009. The later project record lists a construction bid of $4,236,603.

SPS New England took over the work. The state’s design-build project list (PDF, 224 kB, page 1) identifies the team as SPS/Bayside Engineering. In this arrangement, the project team handled both design and construction.

A January 26 update on Greater Grafton described the intended bridge as two prefabricated concrete arches faced with stone from the previous structure. It also described the Historical Commission review of the design.

Access to nearby land remained unfinished business.

Awarding a construction contract did not settle every arrangement needed to reach the work site. At the February 3 Board of Selectmen meeting (PDF, 157 kB, page 4), the town engineer reported that the project needed four rights of way. Two had been secured, and two homeowners still needed to grant access. The board approved an extension of the bridge agreement.

These permissions concerned the use of property needed for the project. The minutes record the outstanding arrangements without explaining each homeowner’s position or assigning responsibility for the broader construction delay.

There was progress the following month. At the March 3 meeting (PDF, 184 kB, page 1), town administrator Tim McInerney reported that MassHighway had obtained an easement for property needed to access the bridge. A MassHighway representative had told the town that work was expected to be under way by April.

Town officials pressed for sidewalks.

As construction approached, the question of who could use the rebuilt crossing became more prominent. Greater Grafton’s March 18 report said the current design did not include sidewalks and that selectmen had sent a letter requesting them.

The report quoted Mary Ann Cotton’s objection: “It’s absurd to build a bridge without a sidewalk.” It also recorded Peter Adams’ concern that another change could prolong the work. Their exchange captured the problem facing the board: officials wanted pedestrian access while also wanting a long-disrupted road connection restored.

The issue remained unresolved in the April 7 minutes (PDF, 225 kB, page 6). McInerney said he had discussed the bridge with MassHighway and was waiting for written confirmation of its position that adding sidewalks would require another bidding process. Cotton planned to seek more detailed information.

That record establishes a discussion about design changes and their possible effect on the contract. It does not establish the final sidewalk layout.

Expectations shifted toward an early-July opening

The schedule discussed early in the year was less immediate. The January Greater Grafton update anticipated approvals through the spring and construction in late spring and summer. It described an incentive for completion by the end of August and a December deadline. These were the expectations reported in January, before the later opening announcement.

Confusion about timing was still evident in local coverage on February 19. When state Sen. Michael Moore described work starting in the fall, selectmen objected that they had understood it would be finished by then.

By June, town officials were discussing a much nearer finish. McInerney’s report in the June 2 meeting record (PDF, 227 kB, page 1) said the bridge was expected to be finished by July 1.

The June 30 concrete review

Officials announced the postponement that morning, ahead of the planned afternoon opening. A Greater Grafton post dated June 30 explicitly noted that the opening story had been revised after an email from the state that morning.

The original report quoted Executive Office of Transportation spokesman Adam Hurtubise explaining that the design-build team would submit calculations and documentation on whether the concrete could remain. MassHighway structural engineers would then make a recommendation. The announced review concerned the suitability of material already installed.

The report described crews painting traffic lines, with paving recently finished and some stonework planned after reopening. Cotton, who lived nearby, also anticipated concerns about faster through traffic and expected police monitoring.

The recovered announcement does not identify the precise concrete specification at issue or supply the engineers’ eventual decision. It therefore cannot establish what corrective work, if any, followed the review.

What the cost records mean

The interrupted project and the later contract left several dollar figures in the historical record. The state database distinguishes a construction bid from the construction contract value it currently displays:

Project phase

Construction bid

Displayed construction contract value

Original replacement project

$1,744,631

$1,952,294

Later bridge project

$4,236,603

$5,000,000

The later bid conveys the scale of the restarted project. The displayed contract figures require more care: these records do not provide a complete accounting of payments across both phases. Adding the entries would not establish the final amount spent on the bridge. The $5 million figure also should not be read as the estimate residents heard on June 30, 2009.

What later records show

The replacement was completed. The state bridge inventory dates the concrete arch to 2009 and records a length of 27.2 meters, compared with 23.8 meters for the removed masonry bridge.

The project subsequently received professional recognition. The New England chapter of the Construction Management Association of America listed Pleasant Street over the Blackstone River among its infrastructure award winners at its April 28, 2010 ceremony, according to its Summer 2010 newsletter (PDF, page 4).

The Central Massachusetts Regional Planning Commission’s 2012 transportation plan (PDF, 94.4 MB, printed page III-32) provides another dated record. Its bridge-project table, using MassDOT data from November 2010, lists the Pleasant Street crossing as complete.

The exact day traffic resumed after the June 30 postponement remains unverified.


Historical source note: This is a new Grafton Times account based on the recovered original report, contemporary Greater Grafton coverage, town board minutes, and later state and regional documents. The original survives in a July 3, 2009 archive capture. Its masthead date is not an established publication date. The illustration is a conceptual bridge-and-river scene, not a photograph or exact reconstruction of Pleasant Street Bridge in 2009.